Introduction
Ever priced a job that looked fine on paper, then the crew lagged and your margin evaporated? Thatâs usually a production rate problem. Production rates are the backbone of accurate bids, realistic programmes, and sensible crew sizing. In this guide, weâll break down what production rates really are, how to build them from your own work, how to adjust for real-world conditions, and how to apply them to pricing and scheduling. Along the way, Iâll share the field-tested steps I use with crews so your rates hold up on site, not just in a spreadsheet. Youâll finish with a set of rates you trustâand know how to keep them sharp.
Table of Contents
Key Takeaways
- Build rates from your own jobs; donât rely only on book values. In general, 3â5 measured jobs per task gives a dependable baseline.
- Adjust rates for reality: access, height, weather, learning curve, and inspection hold points commonly shift output by 10â30%.
- Apply rates directly: Quantity á Rate = Duration. Duration à Crew Cost = Labour Allowance. Keep it simple and consistent.
- Track daily output and causes of delay. Many contractors find small logistics fixes can lift output by 10â20% without adding people.
- Capture the measured scope by voice and turn it into a proposal quickly. Tools like Donizo help you go from site notes to signed work faster.
What Production Rates Are And Why They Matter
Production rates define how fast your team converts materials into finished work. Think âmetres of trench per dayâ, âsquare metres painted per hourâ, or âlinear metres of skirting fitted per dayâ. If your rate is wrong, your price, programme, and cashflow follow it off a cliff.
Problem
- Many contractors copy rates from a book or an old job and never verify them. Then site conditions change and the hours explode.
- Itâs common for crews to lose time to poor staging, unclear drawings, or shared access. In general, these can cut output by 15â30% if ignored.
Solution
- Define each task clearly, pick the right unit, and measure your actual output over several days and jobs.
- Separate rates by context: ground floor vs. above second storey, occupied vs. empty, new build vs. retrofit.
Example
- Task: Paint new plaster walls in a school corridor. Unit: square metres. Baseline context: ground floor, clear access, taped edges provided, good lighting. Measured rate: 120â160 m² per painter per day under baseline conditions.
Set Your Baseline: A Five-Step Field Method
Step 1: Pick The Task And Unit
- Choose one clearly scoped task at a time (e.g., âlay 600 x 600 porcelain tile including groutâ).
- Select the unit youâll always use (m², lm, mÂł, fixtures, doors).
Step 2: Define The Baseline Conditions
- Access, height, substrate, staging, material type, and finish level.
- Write it down. If your baseline is vague, your rate will wander.
Step 3: Measure On Live Work
- Track start/stop time, crew size, and quantity completed each day.
- Exclude non-productive time you canât eliminate (e.g., lunch), but note delays you could fix (e.g., material fetches).
- In general, measuring over 3â5 days smooths out noise and gives a stable daily average.
Step 4: Calculate The Rate
- Daily output per person = Quantity completed á People á Days.
- Baseline rate = median of your measured days. Median handles âone bad dayâ better than a simple average.
Step 5: Record The Context And Photos
- Capture a few photos and notes so you remember what âbaselineâ looked like.
- Use voice notes on site to describe details quickly. With Donizo, those voice notes can become a clear, professional proposal for the same type of work, then sent for e-signature.
In general, contractors who collect even basic field data for two weeks can trim estimating time by 20â30% on repeat work because they stop second-guessing allowances.
- Measure wheel, laser, or cloud point if available
- Simple time sheet (paper or phone form)
- Spreadsheet for rates library
- Phone camera for context photos
Real-World Example: Stud Framing
- Crew: 3 carpenters
- Scope: 70 lm of 92 mm metal stud walls to 2.7 m height, ground floor, straight runs, single layer board later
- Days worked: 1.5
- Output: 70 lm á 1.5 days = 46.7 lm/day crew; per person = 15.6 lm/day
- Baseline rate recorded: 15â18 lm/person/day for similar conditions
Adjust For Real-World Conditions
Problem
Your baseline wonât hold everywhere. Stairs, lifts, tight sites, occupied areas, or winter weather all bite into output. Many contractors forget to derate and end up chasing hours.
Solution
Create adjustment factors you apply consistently. Youâre not guessingâyouâre planning for conditions you know will slow you down.
Common Adjustment Ranges (use your own data where possible)
- Access and Height: In general, above second storey without lift can reduce output by 10â25% due to handling and travel time.
- Congested/Occupied Areas: Commonly, productivity drops 15â30% to protect finishes, work out of hours, and coordinate.
- Weather (External): In general, light rain or wind can reduce exterior painting and roofing output by 10â20%; heavy weather by 30â50%.
- Learning Curve/New Crew Mix: Many contractors report a 15â25% improvement from day 1 to day 3 on repetitive tasks as the crew settles in.
- Inspections/Hold Points: Commonly add 5â10% time where frequent checks are required.
Quick Mitigation Wins
- Stage materials within 10â15 metres of the workface; in general this recovers 10â20% lost time on repetitive tasks.
- Pre-assemble or pre-cut where safe and compliant.
- Confirm access windows and coordinate with other trades daily.
Example
- Baseline tiling: 18 m²/tiler/day
- Job conditions: level 3 (no lift for part of programme), occupied below, strict clean-up
- Adjustments applied: access -15%, occupied -10% â effective rate â 18 Ă 0.75 = 13.5 m²/day
Use Rates To Price, Schedule, And Size Crews
Problem
Good rates on a shelf donât help if they never make it into your numbers or programme. Many contractors estimate by âfeelâ, then discover the programme is unrealistic.
Solution
Run everything through one simple chain: Quantity â Rate â Duration â Cost â Price.
Estimating Labour
- Duration (person-days) = Quantity á Rate per person
- Labour cost = Duration Ă Day cost per person
- Add materials, plant, prelims, overhead, and margin on top.
Example
- Paint 1,200 m² at 140 m²/painter/day baseline
- Duration = 1,200 á 140 = 8.6 painter-days â with 3 painters â 2.9 working days
- Labour cost = 8.6 Ă ÂŁ240/day = ÂŁ2,064 (before overheads and margin)
Scheduling And Crew Sizing
- Programme duration (days) = Person-days á Crew size
- Required crew = Person-days á Target days
Example
- Framing 300 lm at 16 lm/person/day â 18.75 person-days
- Target 5 working days â 18.75 á 5 â 3.75 â staff with 4 carpenters
In general, aligning programme durations to measured rates reduces mid-job re-sequencing by 20â30% because handovers stop colliding.
Turn Measured Scope Into Clear Proposals
- Capture the scope while youâre on site using voice and photos.
- Use Donizo to convert those notes into a branded PDF proposal, send it to the client, and collect a legally binding e-signature.
- When accepted, convert to an invoice in one click and track payments if youâre on a paid planâkeeping the admin lean while you focus on delivery.
Track And Improve: From Daily Output To Company Standards
Problem
Rates decay if you donât maintain them. New tools, different materials, and changing site setups all affect output. If you donât track, you end up repeating the same mistakes.
Solution
Close the loop: capture daily output, review weekly, and update the rates library with context.
What To Track Daily (Simple Is Best)
- Quantity completed by task
- Crew size and hours
- Major delays (material staging, design change, shared access)
- Photos of setup and finish
In general, crews that note top-three delays each day find 1â2 quick fixes that lift weekly output by 10â15% without extra labour.
Weekly Review Template
- Compare planned vs. actual output for two key tasks
- Identify the biggest variance and its cause
- Decide one change for next week (staging, access, tooling, sequence)
Quick Impact Table
| Feature | Current State | Improvement |
|---|
| Staging | Materials 40â60 m away | Stage within 10â15 m; in general adds 10â20% output |
| Access | Lift shared, long waits | Time slots booked; typically halves waiting time |
| Supervision | Late starts, unclear targets | Daily start brief with target m²/lm; commonly adds 5â10% |
| Tooling | Old blades, blunt bits | Replace per spec; often saves 5â10 minutes/hour |
Example
- Drylining gang improved from 110 m²/day to 135 m²/day in two weeks by staging boards closer and setting a daily target. Thatâs roughly a 20â25% uplift without adding headsâcommon when logistics are sorted.
Frequently Asked Questions
Whatâs A âGoodâ Production Rate For My Trade?
Thereâs no universal number. Start with a sensible baseline from your own jobs. In general, youâll see typical ranges like 10â20 m²/tiler/day, 100â160 m²/painter/day, or 12â18 lm/carpenter/day for skirting under baseline conditions. Measure your work, then adjust for access, height, and occupancy.
How Many Jobs Should I Measure Before Trusting A Rate?
In general, 3â5 jobs or 5â10 solid days of measurement per task gives you a dependable median. Keep adding data and refresh the baseline yearly or when materials or methods change.
How Do I Apply Weather And Access Adjustments Without Guessing?
Create standard bands for your business. For example: exterior in light rain/wind: -10â20%; heavy weather: -30â50%; above second storey without lift: -10â25%. Tune the bands using your own recorded outputs.
Can I Use Production Rates For Small One-Off Jobs?
Yesâespecially for repetitive tasks like doors, fixtures, or small patches. For tiny tasks, include a set-up allowance (commonly 30â60 minutes) because set-up dominates the time on small jobs.
How Does Donizo Fit Into This?
Use your measured rates to scope work on site by voice in Donizo. It turns those notes and photos into a professional proposal you can email immediately, collect a legally binding e-signature, and, once accepted, convert to an invoice in one click. That reduces admin and helps you get from walk-through to signed job faster.
Conclusion
Reliable production rates turn uncertainty into control. Measure a clear baseline on live work, adjust for real-world conditions, and run those rates straight into your pricing and programme. Review weekly, fix the simple bottlenecks, and keep your library current. When youâre ready to turn that scoped work into a clean proposal, record the details by voice and let Donizo generate and send a branded PDF for e-signatureâthen convert to an invoice when the client accepts. Fewer guesses, fewer surprises, better margins.